May 2024 - An incredibly active and productive 3 months results in final delivery of all equipment and placement of the majority of drying and pelletizing system on foundations. Exactly 12 months since "Notice to Proceed". Our target of first pellet delivery this fall remains on target, despite a wetter and stormier spring than usual.

February 2024 - The new year is off to a busy start at our site. PDI is completing site piling, following up with concrete foundations. As construction transitions to above-ground work, the site will really start transforming in the next two months.

October 2023 - Construction continues to progress at our site with concrete being poured. Patch Group has finished site prep and grading, and the project is focused on piles, roads, and foundations. We are excited to share more project photos with you as our project progresses forward!

August 2023 - We are excited to share that we started site clearing and grading at our site! Thank you to Player Design Inc. and Patch Group for getting us started on the right foot. Patch Group is a local Louisiana contractor selected to complete all our site clearing, grading, and road work. We are excited to keep moving with construction and continue to hire local contractors for the next phases of construction!

July 2023 - Groundbreaking event at the site

May 2023 - Full Notice to Proceed delivered to contractors